● TransPacific
Parkway Realignment - completed
The
$1.35 million project combined two road/rail crossings
into a single, signalized crossing to create a safer
intersection for visitors to the south end of the Oregon
Dunes National Recreation Area and nearby industrial
sites. The project was funded
with grant funds from the
Federal Safe, Accountable, Flexible, Efficient
Transportation Equity Act: A Legacy for Users (SAFETEA:LU)
and the Oregon Transportation Investment Act III (OTIA
III).
Knife
River Materials of Coos Bay won the construction bid
award of $1.1 million.
● Coos
Bay Rail Line Rehabilitation
The
Oregon International Port of Coos Bay is overseeing the
$30 million rehabilitation of the 133-mile Coos Bay rail
line. To date, the Port has completed the majority of
the repairs to the nine tunnels. Contractors also have
removed vegetation, debris and sand; in addition to
completing geometry testing of the rails.
|
Company |
Company Location |
Contracted Work |
Contract Amount |
|
Conrad Wood Preserving Co. |
North Bend, OR |
Wooden crossties |
$3,331,080.00 |
|
LRL Construction Co., Inc. |
Tillamook, OR |
Tunnel repair phase 3 |
$2,408,714.60 |
|
RailWorks Track Systems, Inc. |
Chehalis, WA |
Emergency track repairs |
$741,459.00 |
|
Knife River |
Coos Bay, OR |
Sand removal |
$336,340.00 |
|
Reforestation Services, Inc. |
Salem, OR |
Vegetation control |
$180,000.00 |
|
ENSCO |
Springfield, VA |
Geometry testing |
$59,711.00 |
|
Crouch Engineering, PC |
Brentwood, TN |
Bridge repair |
$45,000.00 |
|
Hartsell Construction |
Junction City, OR |
Road building/Tunnel 13 repair |
$34,330.00 |
|
Sperry Rail |
Danbury, CT |
Rail flaw detection |
$20,896.00 |
|
Kyle
Electric |
Coos Bay, OR |
Coos
Bay Rail Bridge elect. |
$120,911.00 |
|
Mountain States Consulting |
Salem, OR |
Personal Services |
$100,000.00 |
|
H&S Construction |
Roseburg, OR |
Personal Services |
$76,952.00 |
|
Michael Webb Inc. |
Gresham, OR |
Bridge work, crossing inspections |
$50,000.00 |
|
Osmose Railroad Services |
Madison, WI |
Emergency bridge repairs |
$138,684.00 |
|
Knife River |
Coos Bay, OR |
Ballast
processing/delivery |
$584,011.00 |
|
Babb
Const. DBA Delta Construction Co. |
Eugene, OR |
Ballast
processing/delivery |
$287,280.00 |
|
|
|
|
|
|
Total contracts to date |
|
|
$8,515,368.60 |
|
Funding 2009-present |
Loan |
Grant |
Use |
|
State of Oregon |
$5,400,000 |
|
Rail line purchase |
|
SAFETEA:LU |
|
$7,200,000 |
Rail line purchase |
|
ConnectOregon
I |
|
$4,000,000 |
Rail line purchase |
|
American Recovery & Reinvestment
Act 2009 |
|
$2,500,000 |
Tunnel repair |
|
Oregon Lottery HB5054 |
|
$3,500,000 |
Tunnel/track structure |
|
ConnectOregon
III |
|
$7,900,000 |
Tunnel/bridge |
|
TIGER II |
|
$13,500,000 |
Track structure |
|
SAFETEA:LU |
|
$2,500,000 |
Marine-benign treated railroad
ties |
|
Ore. Dept. Transportation &
Federal Railroad Admin. |
|
$1,000,000 |
Signalized crossings |
|
Totals |
$5,400,000 |
$42,100,000 |
|
|